Syl Apps Youth Centre BAS Upgrade
Captured Image: Aug 2019 © 2021 Google
Project Description: The building Automation System (BAS) in this facility was upgraded partly and client decided to renew the rest of the system and integrate them all as one system.In this project, Pact Enginerring provided engineering and commissioning services to renew the old BAS and integrate with the recently renewed system.
Client: | | Kinark Child and Family Services | | Colliers Project Leaders | | CBRE | |
Location: | Oakville, ON |
Start-Date | Nov 2017 |
Completion-Date | Jun 2019 |
Construction Budget: | $340,000 |
General Contractor: | Solness inc |
Design/Compliance Consultant: | Pact Engineering |
Commissioning Consultant: | Pact Engineering |