Project Description: The Huronia Regional Centre (HRC) is a landmark facility on a prominent 107-hectare site. The site contains 50 buildings, ranging in age from the mid-19th to the late 20th century. A centralized steam plant provides heating into HRC site. The steam boilers in the steam plant are in poor condition and requires extensive maintenance to keep it operable. Therefore one of the incentive to decentralize the heat generating plant is to avoid such concern.
Buildings B44 and B45 projects have been initiated to decommission of the existing steam heating system and setup of multiple hydronic and de-centralized heating plants in these buildings, based on the recent Heating Plant study.

Client: | Infrastructure Ontario (IO) | | Colliers Project Leaders | | CBRE |
Location: Orillia
Start-Date Aug 2018
Completion-Date Feb 2020
Construction Budget: $1,200,000
General Contractor: Civil Underground & Excavation Company
Design/Compliance Consultant: FxD Performance
Commissioning Consultant: Pact Engineering