HRC OPP Academy Residence and Orillia Courthouse New Heating Plant
HRC Map Data: © 2021 Google
Project Description: The Huronia Regional Centre (HRC) is a landmark facility on a prominent 107-hectare site. The site contains 50 buildings, ranging in age from the mid-19th to the late 20th century. A centralized steam plant provides heating into HRC site. The steam boilers in the steam plant are in poor condition and requires extensive maintenance to keep it operable. Therefore one of the incentive to decentralize the heat generating plant is to avoid such concern.
OPP Academy Residence building and Orillia Courthouse new heating plant projects have been initiated to decommission of the existing steam heating system and setup of multiple hydronic and de-centralized heating plants as well as humidifiers in these buildings.
Client: | | Infrastructure Ontario (IO) | | Colliers Project Leaders | | CBRE | |
Location: | Orillia |
Start-Date | Aug 2017 |
Completion-Date | May 2019 |
Construction Budget: | $2,500,000 |
General Contractor: | Rutherford Contracting |
Design/Compliance Consultant: | John R. Hamalainen Engineering |
Commissioning Consultant: | Pact Engineering |